Sunday 4 October 2015

Bahrain causeway project on fast track

Manama, August 20, 2012


Work on one of Bahrain's biggest infrastructure projects, the North Manama Causeway, is expected to be finished in next May, ahead of its July deadline, said senior officials.

Works Ministry officials said it is now operating two shifts per day after the number of onsite workers had been increased to 750.

A total of 2,060 of 2,468 concrete blocks have been installed and work on the remaining blocks is due for completion in December, the officials stated.

The new causeway will boost traffic movement to accommodate 120,000 cars per day while flyovers will accommodate 50,000 cars per day, they added.-TradeArabia News Service

Tags: Bahrain | Manama | causeway |

More Construction & Real Estate Stories

calendarCalendar of Events