Aldar's residential projects on track

ABU DHABI, April 27, 2016

Aldar Properties, a leading real estate developer in Abu Dhabi, UAE, said work on all its residential projects in the capital Abu Dhabi - Al Hadeel, Ansam, Al Merief, Nareel Island - was going as per schedule with steady progress being made on the foundations, and structural and MEP (mechanical, electrical and plumbing) work.

West Yas, the Abu Dhabi developer’s first villa community project on the iconic Yas Island, too has been witnessing solid activity over the last few months with all precincts, marine, electrical, lighting and telecommunications work on track.

Talal Al Dhiyebi, the chief development officer, said: "The demand for high quality residential units and an enriched community living experience is greater than the supply in the market. This informs our strategic approach towards developing best in class residential communities."

"It is important for us at Aldar that we work closely with our contractors to deliver these projects on time, thus supporting the sustained demand as well as the long-term economic and social development of Abu Dhabi," he noted.

At Shams Meera, Aldar’s first mid-market focused project, the enabling teams are on site and progressing well with the shoring, piling, and excavation of the three-level basement. Authority NOCs are in process, along with the tendering for the main contract which is expected to awarded during the quarter.

Al Dhiyebi said the construction of the Aldar Academies’ operated school is nearing completion and it will be operational for the beginning of the 2016 – 2017 academic year.  

Infrastructure development at Shams Abu Dhabi on Al Reem Island, is progressing well with the South Canal now open.

During the last quarter, Aldar awarded contracts for the closed canal, and pre-concept designs were submitted for the central park. The east sandy beach has now been completed along with the Repton School area.

Within the Al Raha Beach development, following the completion of the phase one Al Dana infrastructure, substantial works were completed on the second phase, which includes landscaping and road embankment, sewer works, dredging works, storm water networks and district cooling, said the Abu Dhabi developer.

Testing is currently underway on irrigation networks, while maintenance works have already commenced for the existing landscaped areas in the public spaces, stated Aldar.  

At Al Falah Town Centre, general excavation work is now complete with final finishes being made across storm water works, potable water, irrigation, telecoms, electrical, street lighting and substations, it added.-TradeArabia News Service




Tags: Aldar | Yas Island | Projects | residential |