Tuesday 23 April 2024
 
»
 
»
Story

Limitless achieves key Dubai project milestones

DUBAI, December 23, 2017

Dubai-based developer Limitless said its Downtown Jebel Ali master development has reached more new milestones with Zone 2 infrastructure ready and the first substation handed over to Dubai Electricity and Water Authority (Dewa). 
 
All underground utilities are now complete at Zone 2 of the 200 hectare mixed-use development, while 90 per cent of work is finished at Zone 4 and 70 per cent in Zone 3, said a statement from Limitless.
 
Road construction is also complete at Zone 2, and underway at Zones 3 and 4. All infrastructure work at Downtown Jebel Ali is on track for completion in 2018, it stated.
 
Meanwhile, a 132 kv substation was completed and handed over to Dewa in October. 
 
News of these major milestones come three days after Limitless announced an early repayment of Dh412.4 million ($112 million) to banks and trade creditors. 
 
Ali Rashid Lootah, the chairman of Limitless, said: "Downtown Jebel Ali has seen major progress in the last few months, and these new milestones reinforce our commitment to the investors who share our vision for our flagship master community. 2017 has been a highly successful year for Limitless, and we look forward to even greater achievements in 2018 and beyond."
 
Downtown Jebel Ali has more than 300 third party plots that will contain a mixture of apartment blocks, hotels, offices and retail developments. Many are already operational or under construction. 
 
Stretching 11km along Sheikh Zayed Road, the development is close to Jebel Ali Free Zone and within easy reach of Abu Dhabi, Dubai World Central Airport, the Expo 2020 site and a key attractions in Dubai.-TradeArabia News Service



Tags: Dubai | project | limitless | Infrastructure |

More Construction & Real Estate Stories

calendarCalendar of Events

Ads