Dubai's Al Khawaneej Road project 60pc completed

DUBAI, January 30, 2021

Dubai's Roads and Transport Authority (RTA) has announced that work is moving at a steady pace on the Al Khawaneej Road Improvement Project which is now 60 per cent complete. 
 
The project works include the construction of three intersections or service roads extending 23 km along Al Khawaneej and Al Amardi Roads, it stated. 
 
Al Khawaneej Roads Project is one of the key strategic projects for improving the links between Dubai and Sharjah through the improvement of vertical roads linking with the Emirates Road and Sheikh Mohammed bin Zayed Road up to Airport Street, said RTA in its statement. 
 
The project will also accommodate the current and projected growth of traffic. Upon completion, it will slash the travel time between Emirates Road and Sheikh Mohammed bin Zayed Road from 25 minutes to 9 minutes, and the waiting time at the junction of Al Khawaneej-Sheikh Zayed bin Hamdan Al Nahyan Roads (Al Khawaneej Roundabout) from 330 seconds to 45 seconds. 
 
"It will double up the capacity of the junction from 8,000 to 16,000 vehicles per hour. Replacing the roundabout at the intersection of Al Khawaneej-Al Amardi Roads by a surface junction will halve the waiting time from 120 seconds to 60 seconds," stated Mattar Mohammed Al Tayer, Director-General, Chairman of the Board of Executive Directors of RTA.
 
It follows the opening of the Tripoli Street Improvement Project, providing a link between Sheikh Mohammed bin Zayed Road and Emirates Road. 
 
The opening of this 12-km road eased the traffic flow, improved the entry points at Al Warqa and Mirdif along Tripoli Road, and improved the overall safety along the corridor.
 
On the work progress, Al Tayer said: "The completion rate reached 82 per cent at the underpass intersection of Al Khawaneej Road and Sheikh Zayed bin Hamdan Al Nahyan Road."
 
"The contractor completed the construction works at the closed section of the tunnel and is currently working on the supporting walls of the open section of the tunnel. Works are expected to be completed and the tunnel to be opened for traffic this March," said Al Tayer.
 
According to him, early 60 per cent of the bridge leading to Al Awir has been completed, following the installation of precast bridge parts across Emirates Road in the direction of Abu Dhabi- Sharjah. 
 
"Works are currently under way for the installation of other parts at Al Amardi, which are expected to be completed by the end of this month. Then the contractor will undertake the remaining construction works, such that the bridge will be ready for opening by the end of March this year," added Al Tayer.