Decommissioning provisions for UK offshore windfarms with similar-sized turbines can vary by as much as ten times, highlighting the need for greater transparency and consistency in how the sector estimates future removal costs, according to a new study by Xodus and Evolv Energies.
The whitepaper, Benchmarking Offshore Wind
Decommissioning Provisions, examines figures disclosed in Companies House
accounts for 37 operating UK offshore windfarms between 2019 and 2025, covering
almost 2,500 turbines.
The analysis found that, when normalised per turbine,
provisions for projects using turbines below 4 MW ranged from £180,000 ($235,742)
to £1.83 million. For turbines above 8 MW, the figures ranged from £750,000 to
£4.56 million. Average provisions stood at approximately £900,000 per turbine
for the smallest turbines and £1.5 million for the largest.
Xodus said the scale of the differences between projects
with similar turbine capacities suggests significant variations in the
assumptions and methodologies used to calculate liabilities. It warned that
published provisions should not be considered directly comparable without
understanding the underlying assumptions.
Olivier Mette, Head of Advisory at Xodus, said: “Every
offshore wind project is unique and so we would expect decommissioning
provisions to vary. What stands out, though, is the scale of this variation
between projects using similar sized turbines, which suggests the assumptions
behind the numbers could differ significantly.
“Some estimates appear to be built on greater engineering
definition than others and there is still uncertainty over the regulatory
framework, particularly the required end seabed state, that will shape what
decommissioning may actually require. Published provisions are therefore
difficult to compare and rely on when weighing up life extension, repowering or
removal.”
The study also identified significant changes in reported
liabilities over time. One project's provision increased more than six-fold
during the review period, while other projects recorded more modest increases
and several revised their estimates downwards, partly due to higher discount
rates.
The findings come as the UK's earliest offshore windfarms
approach the end of their original design lives, bringing future
decommissioning decisions into sharper focus. Assuming a 25-year design life,
532 turbines included in the benchmark will reach that point by 2036, rising to
1,285, or just over half of those reviewed, by 2041. Some early projects were
designed for 20 years of operation, potentially bringing forward the
decision-making timeline.
Operators and shareholders will need to assess whether to
extend the life of existing assets, repower sites or proceed with
decommissioning. Xodus said reliable cost estimates will be essential to
evaluating these options.
Elvin Eren, Renewables Advisory Lead at Xodus, said:
“Reported decommissioning provisions are a useful starting point, but they are
discounted estimates built on potentially different assumptions about removal
scope, timing and the condition in which the seabed must be left. Owners,
investors and lenders should treat them as the beginning of due diligence
rather than the answer, and test them against explicit removal scenarios.”
The whitepaper calls for a more transparent and comparable
approach to estimating and disclosing decommissioning costs, with greater
clarity around the assumptions underpinning financial provisions.
It also highlights the relationship between regulatory
certainty and credible cost estimates, arguing that policymakers need reliable
cost information while asset owners require clearer regulatory requirements to
define decommissioning scopes and prepare robust financial forecasts.
Unlike depleted oil and gas fields, where decommissioning is
generally the only viable end-state, offshore wind sites may retain
considerable value beyond their original design lives. Existing infrastructure,
seabed assets and grid connections could support continued electricity
generation through life extension or repowering.
Mette said: “The seabed, grid connections and infrastructure
of offshore wind sites may still hold real value long after turbines reach the
end of their design life.
“Making the right call on those assets depends on decommissioning costs that are transparent and reviewed regularly, and on clearer guidance from regulators. The earlier that each stakeholder works on that together, the better placed the sector will be when those decisions arrive.” -OGN/TradeArabia News Service