Offshore wind decommissioning costs vary tenfold, Xodus study finds

Offshore wind decommissioning costs vary tenfold, Xodus study finds

Decommissioning provisions for UK offshore windfarms with similar-sized turbines can vary by as much as ten times, highlighting the need for greater transparency and consistency in how the sector estimates future removal costs, according to a new study by Xodus and Evolv Energies.

The whitepaper, Benchmarking Offshore Wind Decommissioning Provisions, examines figures disclosed in Companies House accounts for 37 operating UK offshore windfarms between 2019 and 2025, covering almost 2,500 turbines.

The analysis found that, when normalised per turbine, provisions for projects using turbines below 4 MW ranged from £180,000 ($235,742) to £1.83 million. For turbines above 8 MW, the figures ranged from £750,000 to £4.56 million. Average provisions stood at approximately £900,000 per turbine for the smallest turbines and £1.5 million for the largest.

Xodus said the scale of the differences between projects with similar turbine capacities suggests significant variations in the assumptions and methodologies used to calculate liabilities. It warned that published provisions should not be considered directly comparable without understanding the underlying assumptions.

Olivier Mette, Head of Advisory at Xodus, said: “Every offshore wind project is unique and so we would expect decommissioning provisions to vary. What stands out, though, is the scale of this variation between projects using similar sized turbines, which suggests the assumptions behind the numbers could differ significantly.

“Some estimates appear to be built on greater engineering definition than others and there is still uncertainty over the regulatory framework, particularly the required end seabed state, that will shape what decommissioning may actually require. Published provisions are therefore difficult to compare and rely on when weighing up life extension, repowering or removal.”

The study also identified significant changes in reported liabilities over time. One project's provision increased more than six-fold during the review period, while other projects recorded more modest increases and several revised their estimates downwards, partly due to higher discount rates.

The findings come as the UK's earliest offshore windfarms approach the end of their original design lives, bringing future decommissioning decisions into sharper focus. Assuming a 25-year design life, 532 turbines included in the benchmark will reach that point by 2036, rising to 1,285, or just over half of those reviewed, by 2041. Some early projects were designed for 20 years of operation, potentially bringing forward the decision-making timeline.

Operators and shareholders will need to assess whether to extend the life of existing assets, repower sites or proceed with decommissioning. Xodus said reliable cost estimates will be essential to evaluating these options.

Elvin Eren, Renewables Advisory Lead at Xodus, said: “Reported decommissioning provisions are a useful starting point, but they are discounted estimates built on potentially different assumptions about removal scope, timing and the condition in which the seabed must be left. Owners, investors and lenders should treat them as the beginning of due diligence rather than the answer, and test them against explicit removal scenarios.”

The whitepaper calls for a more transparent and comparable approach to estimating and disclosing decommissioning costs, with greater clarity around the assumptions underpinning financial provisions.

It also highlights the relationship between regulatory certainty and credible cost estimates, arguing that policymakers need reliable cost information while asset owners require clearer regulatory requirements to define decommissioning scopes and prepare robust financial forecasts.

Unlike depleted oil and gas fields, where decommissioning is generally the only viable end-state, offshore wind sites may retain considerable value beyond their original design lives. Existing infrastructure, seabed assets and grid connections could support continued electricity generation through life extension or repowering.

Mette said: “The seabed, grid connections and infrastructure of offshore wind sites may still hold real value long after turbines reach the end of their design life.

“Making the right call on those assets depends on decommissioning costs that are transparent and reviewed regularly, and on clearer guidance from regulators. The earlier that each stakeholder works on that together, the better placed the sector will be when those decisions arrive.” -OGN/TradeArabia News Service